{"id":322,"date":"2026-07-29T12:37:43","date_gmt":"2026-07-29T09:37:43","guid":{"rendered":"https:\/\/wellcompletionpro.com\/blog\/?p=322"},"modified":"2026-07-29T14:50:27","modified_gmt":"2026-07-29T11:50:27","slug":"p-a-rock-to-rock-isolation-rigless-execution","status":"publish","type":"post","link":"https:\/\/wellcompletionpro.com\/blog\/p-a-rock-to-rock-isolation-rigless-execution\/","title":{"rendered":"P&#038;A: Rock-to-Rock Isolation &#038; Rigless Execution"},"content":{"rendered":"<p>You\u2019ve got a well to abandon. On paper, it looks straightforward: set a few plugs, cut the wellhead, walk away. But the reality of permanent plug and abandonment (P&#038;A) is anything but simple. This isn&#8217;t just about plugging the pipe; it&#8217;s about restoring the geological seal for geological time.<\/p>\n<p>A P&#038;A design that looks bulletproof on a schematic can fail years later because of a micro-annulus behind casing, a control line creating a leak path through a packer, or a cement plug tagged soft after a poor mud-to-cement displacement. The consequences are sustained casing pressure, environmental risk, and expensive remediation. This job demands absolute certainty.<\/p>\n<h2>The Imperative: Rock-to-Rock Isolation<\/h2>\n<p>The governing objective of permanent abandonment is <strong>cross-sectional, rock-to-rock isolation<\/strong>. This means a barrier that seals the entire wellbore cross-section: the inner tubular bore, every annulus, and the formation face. There must be no vertical flow path between reservoir fluids and the surface\/seabed or shallower permeable zones.<\/p>\n<p>This is a stronger requirement than merely plugging the production string. Historically, the industry&#8217;s most costly abandonment failures came from ignoring the B-annulus, where poor primary cement left a channel. In a permanently abandoned well, this can lead to a slow leak with no one left to manage it.<\/p>\n<h3>Temporary vs. Permanent Abandonment<\/h3>\n<ul>\n<li><strong>Temporary abandonment (TA \/ suspension):<\/strong> The well is secured but intended for re-entry (future workover, sidetrack, or conversion). Barriers must be robust and testable but need not be permanent, and the wellhead is retained. Under BSEE 30 CFR 250.1721, an operator must set specific plugs and is subject to periodic re-assessment.<\/li>\n<li><strong>Permanent abandonment:<\/strong> The well is sealed forever. All barriers must be permanent, gas-tight, and non-degrading. The wellhead and conductor are severed below the mudline (offshore) or below plough depth (onshore).<\/li>\n<\/ul>\n<h2>Navigating the Regulatory Landscape<\/h2>\n<p>The standards landscape for P&#038;A is complex, with different jurisdictions having varying levels of prescription. However, the underlying principles are converging towards robust, verifiable barriers.<\/p>\n<ul>\n<li><strong>NORSOK D-010 (Norwegian Continental Shelf; Rev. 4 \/ 2021):<\/strong> This is arguably the most prescriptive and widely cited barrier standard. It defines the well barrier element (WBE) concept, requires a primary and a secondary (backup) well barrier for every flow path, and specifies element acceptance criteria (EAC). NORSOK&#8217;s philosophy\u2014<strong>two independent, verified, tested barriers<\/strong>\u2014has effectively become the global template.<\/li>\n<li><strong>OEUK Well Decommissioning Guidelines (UKCS; Issue 6\/7):<\/strong> This guidance is performance-based, not prescriptive. Operators justify barrier placement against specific geology rather than following fixed plug lengths. OEUK has extended its guidance to cover CO\u2082 storage and legacy-well assessment.<\/li>\n<li><strong>BSEE 30 CFR 250 Subpart Q (US Outer Continental Shelf, GoM):<\/strong> This regulation is highly prescriptive, with fixed plug lengths for various barrier types.<\/li>\n<li><strong>API standards (API RP 65-3, zonal-isolation, cementing):<\/strong> These underpin the technical detail, with onshore US wells generally following API practice under state regulators.<\/li>\n<\/ul>\n<p>The practical takeaway: NORSOK and BSEE often give you specific numbers for plug length and placement; OEUK tells you to prove it works for your well. Most operators design to the most conservative applicable rule and verify to NORSOK-grade acceptance criteria regardless of jurisdiction.<\/p>\n<h2>Defining a Permanent Barrier: Requirements &#038; Verification<\/h2>\n<p>A permanent well barrier must meet stringent criteria to ensure long-term integrity:<\/p>\n<ol>\n<li>Extend across the full cross-section\u2014the pipe bore and all annuli (rock-to-rock). A cement plug inside casing that leaves an uncemented B-annulus behind it is not a permanent barrier.<\/li>\n<li>Be positioned against a competent formation\u2014ideally impermeable caprock with demonstrated sealing capacity and adequate fracture resistance, not against a permeable or depleted interval. The barrier should straddle the caprock so the seal sits where the geology already wants to hold pressure.<\/li>\n<li>Be impermeable, non-shrinking, ductile, and resistant to the downhole chemical environment (H\u2082S, CO\u2082, brines) for geological time.<\/li>\n<li>Be verified and, where practical, tested.<\/li>\n<\/ol>\n<h3>Plug Length, Position, and Verification<\/h3>\n<p>There is no single global number for plug length; requirements range from about 15 m to 100 m depending on jurisdiction and whether the barrier is a single- or dual-purpose element. Here&#8217;s a breakdown:<\/p>\n<ul>\n<li><strong>NORSOK D-010 (EAC):<\/strong> A cement plug used as a barrier should give at least 30 m (\u2248100 ft) MD of verified, logged cement bond. A reservoir barrier plug is typically set to extend ~50 m MD above the top perforation. Open-hole plugs commonly target ~100 m.<\/li>\n<li><strong>BSEE 30 CFR 250.1715:<\/strong> Prescribes fixed lengths: 100 ft above and below an open-hole zone, casing shoe, or casing stub; 100 ft across perforations (or a 200-ft plug as an alternative method); 200 ft for annular and cast-in-place plugs; and a 150-ft surface plug with its top no deeper than 150 ft below the mudline.<\/li>\n<li><strong>OEUK:<\/strong> Plug length is determined by engineering analysis to achieve isolation across the sealing formation, not a fixed figure.<\/li>\n<\/ul>\n<p><strong>Verification is layered and critical:<\/strong><\/p>\n<ul>\n<li><strong>Tagging:<\/strong> Run in and set weight on the plug top to confirm it is where planned and hard. Industry practice accepts roughly \u00b13 m (\u00b110 ft) of the planned top.<\/li>\n<li><strong>Pressure testing:<\/strong> A positive test (e.g., hold ~1,000 psi \/ 70 bar for 30 min with an acceptable maximum leak-off) and\/or an inflow\/negative test to confirm the barrier holds differential in the flow direction.<\/li>\n<li><strong>Logging:<\/strong> Cement-evaluation logs (CBL\/VDL, ultrasonic USIT\/isolation-scanner) to confirm the annular cement bond behind casing, since a plug is only as good as the cement sheath around the pipe it sits in.<\/li>\n<\/ul>\n<h2>The Three Phases of Abandonment Execution<\/h2>\n<p>The industry standard execution model, reflected in NORSOK, OEUK, and rigless-P&#038;A workflows, divides the job into three distinct phases. This structure matters commercially because the phases have very different rig\/vessel requirements and can be decoupled.<\/p>\n<ol>\n<li><strong>Phase 1 \u2014 Reservoir and intermediate (overburden) abandonment:<\/strong> This is where you isolate the reservoir first, then any intermediate permeable\/hydrocarbon-bearing zones in the overburden. Reservoir abandonment sets the primary and secondary barriers across the producing interval. In a completed well, this usually means pulling or dealing with the completion, killing the well, and placing a cross-sectional barrier\u2014either through the tubing (through-tubing rock-to-rock) or after tubing removal. Overburden abandonment places barriers across any shallower zones with flow potential (charged sands, freshwater aquifers) and across casing shoes and stubs. Phase 1 is barrier-intensive and normally the most technically demanding\u2014it drives whether a rig is needed at all.<\/li>\n<li><strong>Phase 2 \u2014 Environmental \/ surface plug:<\/strong> A single cross-sectional barrier near surface protects shallow zones and the seabed. On subsea wells, this is the phase most amenable to riserless vessel operations, decoupling it from the drilling rig.<\/li>\n<li><strong>Phase 3 \u2014 Wellhead and conductor removal:<\/strong> Sever and recover the wellhead, casing strings, and conductor below the mudline (BSEE: \u226515 ft; UKCS: to leave a clear seabed) using mechanical, abrasive-jet, or explosive cutters. Debris clearance and a seabed survey close out the well.<\/li>\n<\/ol>\n<h2>Proven Placement Techniques<\/h2>\n<h3>Balanced Cement Plug<\/h3>\n<p>The workhorse of P&#038;A. Cement slurry is spotted through a stinger or drill pipe so that the hydrostatic heads inside and outside the pipe are equal (&#8220;balanced&#8221;) when pumping stops. The pipe is then pulled slowly above the cement top and reverse-circulated clean, leaving a stationary plug. Success hinges on mud removal\u2014pump adequate spacer, use a base-of-plug support (viscous pill, mechanical plug, or bridge plug), and pull dry to avoid swabbing.<\/p>\n<h3>Worked Example \u2014 Balanced Cement Plug Volume<\/h3>\n<p>Let&#8217;s walk through placing a 1,000 ft balanced cement plug across a casing shoe in a 6.25 in open hole, spotted through a 4 in drill-pipe stinger with a 2-7\/8 in tail. Cement 16.0 ppg; spacer 10.5 ppg.<\/p>\n<p>Capacity factors use the standard constant 1029.4 (bbl\/ft = D\u00b2[in]\/1029.4):<\/p>\n<ul>\n<li>6.25 in hole capacity: 6.25\u00b2 \/ 1029.4 = 0.03794 bbl\/ft<\/li>\n<li>4 in DP capacity (ID \u2248 3.34 in): \u2248 0.01084 bbl\/ft<\/li>\n<li>Annular capacity (6.25 in hole \u00d7 4 in DP OD): (6.25\u00b2 \u2212 4\u00b2) \/ 1029.4 = (39.06 \u2212 16.0)\/1029.4 = 0.02240 bbl\/ft<\/li>\n<\/ul>\n<p><strong>Step 1 \u2014 Cement volume for a 1,000 ft plug (open hole):<\/strong><br \/>\nCement = plug length \u00d7 hole capacity = 1,000 ft \u00d7 0.03794 = 37.9 bbl<\/p>\n<p><strong>Step 2 \u2014 Height of that cement with pipe still in hole (to know how far to pull):<\/strong><br \/>\nHeight with pipe in = cement volume \/ (DP capacity + annular capacity)<br \/>\n= 37.9 \/ (0.01084 + 0.02240) = 37.9 \/ 0.03324 \u2248 1,140 ft<br \/>\nSo while the string is in the cement, the column stands ~1,140 ft; after pulling the stinger clear it collapses to the 1,000 ft plug.<\/p>\n<p><strong>Step 3 \u2014 Balancing spacer:<\/strong> Pump a spacer ahead (e.g., 50 bbl) to clean the hole ahead of cement, and a calculated spacer behind the cement so heads balance. Behind-spacer volume is chosen so its height inside the pipe matches the spacer height in the annulus. In the standard reference case this yields ~23 bbl behind.<\/p>\n<p><strong>Step 4 \u2014 Displacement:<\/strong> Displace with mud equal to the pipe capacity above the top of the behind-spacer. In a typical example, this is \u224869 bbl, slightly underdisplaced to avoid over-displacing (which would U-tube cement up the annulus and unbalance the plug).<\/p>\n<p><strong>Pumping sequence:<\/strong> 50 bbl lead spacer \u2192 37.9 bbl cement \u2192 ~23 bbl trailing spacer \u2192 ~69 bbl mud \u2192 stop, pull stinger slowly above the cement top, reverse-circulate excess, then WOC (wait on cement) before tagging and pressure-testing.<\/p>\n<p><em>Practitioner notes:<\/em> Always add an excess factor (10\u2013100 %) for hole washout\/losses in open hole; under-displace by ~\u00bd bbl to keep cement from over-U-tubing; and never pull the stinger through green cement faster than the slurry can fall back, or you swab the plug apart.<\/p>\n<h3>Mechanical Plugs and Bridge Plugs<\/h3>\n<p>Bridge plugs (retrievable or permanent) and cement retainers provide a mechanical foundation to set cement on, a testable element, and often one of the two required independent barriers. BSEE explicitly requires at least one mechanical barrier in the central wellbore. Modern deep-set metal (expandable) plugs can act as standalone verified barriers.<\/p>\n<h3>Section Milling: The Traditional Route<\/h3>\n<p>Section milling is the traditional route to a rock-to-rock barrier when the annular cement is absent or channeled. It involves milling out a section of casing (typically 30\u201360 m), under-reaming the exposed formation, and placing a cement plug across the open hole so cement contacts formation on all sides. While effective, it is slow, generates large volumes of steel swarf that must be circulated out and disposed of, wears out mill knives (often requiring multiple runs), and consumes expensive rig time\u2014frequently the single biggest cost item on a difficult abandonment.<\/p>\n<h3>Perforate, Wash, and Cement (PWC): The Modern Standard<\/h3>\n<p><strong>Perforate, Wash, and Cement (PWC)<\/strong> is the dominant modern alternative to section milling for creating a cross-sectional barrier without removing casing:<\/p>\n<ol>\n<li><strong>Perforate:<\/strong> Perforate the casing across the barrier interval to open communication with the annulus.<\/li>\n<li><strong>Wash:<\/strong> Circulate wash fluid through the perforations to remove mud\/solids from the annulus. Cup-based tools isolate the interval with cups; jet-based tools use high-velocity nozzles and rotate continuously without a swivel.<\/li>\n<li><strong>Cement:<\/strong> Place cement across the perforations in a pump-and-pull sequence so it fills both the bore and the annulus, forming a single rock-to-rock plug with the casing left intact.<\/li>\n<\/ol>\n<p>PWC is markedly faster than section milling, generates no swarf, avoids associated BOP-contamination and personnel hazards, and can be single-trip. One operator reported a dual-casing PWC application saving 66 hours versus milling. Jet-based PWC now has the largest field track record, with ~150 deployments documented at Ekofisk, Norway, and is rated &#8220;field-proven&#8221; on Offshore Norge&#8217;s P&#038;A technology roadmap.<\/p>\n<p>Verification traditionally means drilling out the internal cement and running a CBL plus a pressure test. However, a qualification-matrix \/ track-record approach (after a minimum of three drilled-and-logged successes with identical parameters, backed by CFD validation) allows the drill-out\/log to be waived on subsequent identical wells\u2014a major time saver on campaigns. Per NORSOK EAC (Table 61, 2021), a PWC\/cement barrier is accepted with a cement plug extending 50 m MD above the top perforation and a minimum 30 m MD of verified bonded cement for single-barrier duty.<\/p>\n<h3>Through-Tubing Rock-to-Rock (TTRR)<\/h3>\n<p>Performing PWC (or setting any barrier) through the production tubing, avoiding a full completion pull, is central to rigless\/low-cost P&#038;A. It removes the most expensive step (tubing retrieval, which risks stuck strings and control-line damage) but demands small-OD tools and excellent annular access. Coiled-tubing PWC has seen 16 successful deployments reported in Alaska and Australia.<\/p>\n<h3>Emerging Barrier Materials<\/h3>\n<ul>\n<li><strong>Bismuth-based alloys:<\/strong> These low-melting-point (~273 \u00b0C) eutectic metals are melted downhole (commonly with a thermite heater) and expand ~3 % on solidification, sealing against the pipe\/formation like ice in a crack. They have a density SG \u2248 10, water-like viscosity when molten, and freeze almost instantly (no gel phase). Bismuth resists H\u2082S\/CO\u2082, is non-toxic, and can potentially deliver isolation with shorter plug lengths than cement, deployed rigless. This is attractive for surface plugs and for remediating post-abandonment sustained annular pressure\/gas migration. Qualification for standalone permanent-barrier duty is maturing.<\/li>\n<li><strong>Thermite \/ in-situ melt systems and geopolymer\/resin sealants:<\/strong> These are additional options for specific channels and small annuli, offering specialized solutions where conventional cement may struggle.<\/li>\n<\/ul>\n<h2>P&#038;A Decision Checklist: Before You Pump<\/h2>\n<ul>\n<li><strong>Define the Barrier Objective:<\/strong> Is it temporary or permanent? What flow paths must be isolated?<\/li>\n<li><strong>Identify All Annuli:<\/strong> Have you accounted for the A, B, C, and D annuli? Is there primary cement behind all casing strings?<\/li>\n<li><strong>Know Your Regulatory Minimums:<\/strong> What are the specific plug lengths and verification criteria for your jurisdiction (NORSOK, BSEE, OEUK)?<\/li>\n<li><strong>Assess Formation Competence:<\/strong> Is the chosen barrier placement zone a competent caprock with proven sealing capacity and adequate fracture resistance?<\/li>\n<li><strong>Verify Existing Cement:<\/strong> Don&#8217;t assume. Tag, pressure test, and log existing cement to confirm integrity.<\/li>\n<li><strong>Plan for Contamination:<\/strong> How will you ensure proper mud removal ahead of cement placement? Adequate spacer volume, viscous pills, base-of-plug support.<\/li>\n<li><strong>Consider Completion Complexity:<\/strong> Are there intelligent completion lines, flat-packs, or feed-through packers that will compromise a simple barrier?<\/li>\n<li><strong>Diagnose Sustained Casing Pressure (SCP):<\/strong> If present, what is the source? How will it be killed and remediated before setting the permanent barrier?<\/li>\n<li><strong>Evaluate Rig vs. Rigless:<\/strong> Can any phases (especially Phase 2 &#038; 3, or even through-tubing Phase 1) be moved to a lighter, cheaper spread (HWU, CTU, RLWI vessel)?<\/li>\n<li><strong>Contingency Planning:<\/strong> What if the first plug tags soft, or the pressure test fails? Have backup plans for re-squeezing or alternative techniques.<\/li>\n<\/ul>\n<h2>When Abandonment Gets Complicated: Failure Modes &#038; Lessons<\/h2>\n<p>Older, high-value assets rarely abandon cleanly. The problem wells share recurring features that demand careful planning and execution:<\/p>\n<ul>\n<li><strong>Intelligent \/ Smart Completions:<\/strong> These carry control lines and flat-packs (hydraulic lines, electric cables, fiber) clamped along the tubing and fed through production packers. Each line is a potential micro-leak path across an intended barrier, defeating a clean rock-to-rock seal at the packer. Feed-through packers, while excellent for production-phase isolation, leave the P&#038;A engineer with penetrations to seal. The usual answer is a cross-sectional barrier (PWC or milled section) placed at a depth clear of the flat-pack, or full removal of the completion in that interval.<\/li>\n<li><strong>Annular Barriers and Legacy Cement:<\/strong> A well may show good primary cement on the CBL yet still leak; conversely, a &#8220;poor&#8221; bond may seal. The barrier must be <em>verified<\/em>, not assumed. Where the A- or B-annulus is unsealed, PWC or section milling is often unavoidable to achieve rock-to-rock isolation.<\/li>\n<li><strong>Sustained Casing Pressure (SCP):<\/strong> Pressure that rebuilds on an annulus after bleed-down signals a live leak path\u2014gas migrating through channeled cement or past a failed seal. SCP must be diagnosed and killed before setting the permanent barrier, or the abandonment simply traps a pressurized annulus behind the new plug. Remedies include annular squeeze, PWC across the leaking interval, expandable metal packers, and bismuth-alloy annular plugs specifically marketed for gas-migration\/SCP remediation.<\/li>\n<li><strong>Other Operational Headaches:<\/strong> Scale, wax, collapsed casing, fish, and shallow gas all add trips and risk, often forcing a drilling rig where a lighter vessel was planned. These issues compound NPT and drive costs.<\/li>\n<\/ul>\n<p>The design discipline is the same throughout: identify every potential flow path, assign an independent primary and secondary barrier to each, and verify both. Cut no corners on verification.<\/p>\n<h2>The Economic Reality: Cost &#038; The Rigless Revolution<\/h2>\n<p>Decommissioning is now a defining cost for mature basins. The UK North Sea Transition Authority&#8217;s 2025 update puts total UKCS decommissioning at ~\u00a344 billion (2024 prices), with well abandonment as the single largest category\u2014roughly half of total spend. The scale of the queue is enormous: over 500 wells are already past their original abandonment deadlines, ~1,700 wells are projected inactive by end-2030, and an execution rate of 250\u2013300 wells per year is needed to clear the backlog. Only 103 wells reached final abandonment in 2024, highlighting the challenge.<\/p>\n<h3>Cost and Schedule Drivers<\/h3>\n<ul>\n<li><strong>Rig\/vessel spread rate:<\/strong> A semisubmersible or drillship day-rate multiplied by well duration is the biggest single lever.<\/li>\n<li><strong>Number of barriers and annuli to seal:<\/strong> Every rock-to-rock barrier (especially by section milling) adds days.<\/li>\n<li><strong>Completion complexity:<\/strong> Pulling tubing, control lines, dealing with scale, and contingency for stuck strings.<\/li>\n<li><strong>Water depth, well type:<\/strong> Platform\/subsea\/exploration, and logistics\/weather.<\/li>\n<li><strong>Waste handling:<\/strong> Swarf, NORM (naturally occurring radioactive material) scale, and produced fluids.<\/li>\n<\/ul>\n<h3>Rigless and Riserless P&#038;A<\/h3>\n<p>The central cost strategy is to get off the drilling rig. Two key levers:<\/p>\n<ul>\n<li><strong>Rigless (through-tubing) P&#038;A:<\/strong> Performs reservoir and overburden barriers through the existing tubing using wireline, coiled tubing, or hydraulic workover units\u2014including through-tubing PWC.<\/li>\n<li><strong>Riserless light-well intervention (RLWI) vessels:<\/strong> Perform subsea P&#038;A\u2014especially Phase 2 (surface plug) and Phase 3 (wellhead removal)\u2014from a monohull vessel without a marine riser. SPE case data show that using riserless technology for the surface-plug phase can release ~35 days of semisubmersible-rig time across a six-well campaign, freeing the rig for revenue-generating drilling.<\/li>\n<\/ul>\n<p>Campaign execution (batching similar wells and reusing qualified PWC parameters via the track-record matrix) compounds these savings. The economic logic is simple: a vessel spread can cost a fraction of a rig spread, so every phase moved off the rig\u2014and every drill-out\/log waived by a qualified PWC track record\u2014attacks the largest line item directly.<\/p>\n<h2>The Bottom Line<\/h2>\n<p>Permanent well abandonment is a critical, complex engineering challenge demanding meticulous planning and execution. Focus on achieving <strong>rock-to-rock isolation<\/strong> across all annuli, verify every barrier with robust testing, and leverage modern techniques like PWC and rigless operations to drive efficiency. Ignoring the details, especially the B-annulus or complex completion elements, will lead to costly failures down the line.<\/p>\n<p>Have a question about your well? Reach out via the contact page.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>You\u2019ve got a well to abandon. On paper, it looks straightforward: set a few plugs, cut the wellhead, walk away. [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"closed","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"default","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","ast-disable-related-posts":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"default","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"categories":[7],"tags":[],"class_list":["post-322","post","type-post","status-publish","format-standard","hentry","category-workover-intervention"],"_links":{"self":[{"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/posts\/322","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/comments?post=322"}],"version-history":[{"count":1,"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/posts\/322\/revisions"}],"predecessor-version":[{"id":335,"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/posts\/322\/revisions\/335"}],"wp:attachment":[{"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/media?parent=322"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/categories?post=322"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/wellcompletionpro.com\/blog\/wp-json\/wp\/v2\/tags?post=322"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}